What to take away
- The checklist runs in four stagesbefore you open, before you hire, before every job, and before you leave a site.
- Every item has an evidence row, because an unrecorded answer is the same as no answer six months later.
- Record the office that gave each answer and the date it was given.
- The two items with consequences past paperwork are the utility locate ticket and the boundary line.
Use this as a quote-file control: resolve parcel questions that can change scope or schedule before promising a start date, and record each answer beside the estimate.
Each evidence row has five fields: the item, the proof, the office that issued it, the date, and the person who checked it. For example, a locate ticket row holds the ticket number, its issue and expiry dates, the one-call program that issued it, and the name of the crew lead who matched the dig date to the window.
Before you open
Settle these eight items once, before the first quote goes out. Each one is a tick in the file and a date for the next renewal.
- Business registered with the state in the form you chose, and the renewal date recorded.
- Federal and state tax accounts opened, with the filing schedule written down.
- Contractor licensing settled for your jurisdiction in writing, asking about fencing by name.
- Local operating permit or home occupation permit confirmed with the municipal clerk.
- Insurance placed and the policy wording read, not only the summary page.
- Vehicle and trailer registration confirmed against the combination you actually tow.
- Written safety routine covering digging, lifting, tool use and work above grade.
- Records system live from day one, so job costs and evidence land somewhere findable.
For a California example, the Contractors State License Board (CSLB) lists C-13 Fencing as a contractor classification. Confirm with CSLB whether your scope and contract require a license under California's Contractors State License Law (Business and Professions Code, Division 3, Chapter 9); do not apply that example to another state. In any other state, ask that state's contractor licensing board the same question about fencing by name.
The items above are U.S. rules. Canadian owners can refer to the site's Canadian GST/HST registration guide for that separate jurisdiction.
Before you hire anyone
Four employer steps come before the first person works a job. Complete them in the order shown, and keep the proof in the same file as the quotes.
Before You Hire Anyone
- Employer accounts openedwithholding, unemployment, workers comp
- Employment status decided on the facts
- Wage and hour recordkeeping set up before payroll
- Training record started for each person
- Workers' compensation coverage opened in your state before the first person works.
- Payroll set up with a federal EIN, plus state withholding and unemployment accounts.
- Form I-9 completed and retained for every employee on the first day.
- Subcontractor insurance and license verified in writing, with a certificate on file.
Apply for a federal EIN through the IRS; the paper application is Form SS-4. USCIS Form I-9 is the Employment Eligibility Verification form. Retain each I-9 until three years after the employee's hire date or one year after employment ends, whichever is later.
In California, the Division of Workers' Compensation (DWC), within the Department of Industrial Relations, is the state workers' compensation agency; identify the corresponding agency for your state and confirm coverage requirements. Employers also keep injury and illness records under OSHA's recordkeeping rule, 29 CFR Part 1904, and post the required notices.
Someone you direct hour by hour, and supply with tools and materials, is an employee rather than a subcontractor. Getting that wrong creates back tax and penalty exposure.
Payroll taxes, workers' compensation and paid time off all sit on top of the hourly wage. What they add per hour is worked through in wages and labour costs for a fence contractor business.
Before every job
Eight checks run on every parcel before any work starts. Permits, covenants and locate tickets are parcel-specific and time limited, so none of them carries over from the last job.
Before Every Job
- Boundary established or assumption written into quote
- Permit requirement confirmed with zoning or building
- Height, setback and facing requirements recorded with date
- Post depth or footing standard confirmed against frost
- Association covenants requested in writing
- Utility locate requested through 811, marks photographed
- Locate re-requested if validity window passed
- Site condition photographed before machines go on ground
- Permit pulled for the parcel, with the number on the quote file before work starts.
- Zoning height, setback and facing rules checked for that exact address.
- Homeowner association covenants read, with the relevant pages copied to the file.
- Utility locate requested through 811, and the ticket reference saved before digging.
- Ticket validity window checked against the dig date, and the site marked.
- Property boundary confirmed against a survey or plat, not the old fence line.
- Irrigation, septic and private lines identified by the owner in writing.
- Work above grade planned around fall protection rather than improvised on the day.
Depending on the parcel and work location, ask whether a fence or building permit, zoning approval, or right-of-way or encroachment permit applies. Use the local authority's current application and record the permit type and number; there is no nationwide permit form.
The 811 ticket's validity window depends on the state one-call program. In California, that program is Underground Service Alert, which runs USA North 811 and USA South 811 by region. Record the expiration date and refresh instructions shown on the ticket, or confirm them with that program before digging; there is no single nationwide ticket period.
OSHA's construction fall-protection requirements are in 29 CFR Part 1926, Subpart M, including §§ 1926.501 and 1926.502. Under § 1926.501, an employee at an unprotected edge 6 feet or more above a lower level must be protected by a guardrail system, safety net, or personal fall-arrest system.
Post depth and hole diameter depend on the equipment you run and the soil on site.
Before you leave a site
Close the site before the final invoice goes out. These seven items are the last tick in the file.
- Open holes barriered or backfilled, never left unmarked overnight.
- Gate swing checked across its full arc, with the ground clearance recorded.
- Fasteners and offcuts cleared, with a magnet sweep where the ground is grass.
- Completion photographs taken, including the gate and the gap at grade.
- Final permit inspection requested and passed, with the inspector's sign-off or the permit's closed status recorded.
- Written warranty or workmanship document handed to the customer, with a copy in the file.
- Any variation from the agreed scope recorded and signed before the final invoice.
What the quote file holds at each stage
A file that holds the answers beside the estimate lets anyone pick up the job. Build it in the order the work moves.
- At the estimate, the permit answer, the height and setback reply, the covenant pages and the boundary source, each with the office that gave it and the date.
- Before the dig, the 811 ticket reference with its validity dates, and the owner's written note on irrigation, septic and private lines.
- When a crew works, the insurance certificate for any subcontractor and the I-9 for any employee.
- At closeout, the completion photographs and any signed variation.
What sits behind the list
The reasoning behind each item, and the wider map of who governs what, sits in the compliance side of fence work.
OSHA's safety management page presents recommended practices, not a separate fence-specific regulation. Use its areas, leadership, worker participation, hazard identification, training, and review, as a voluntary safety routine.